At 10:39 AM -0500 27/8/98, W. Wesley Groleau x4923 wrote:
>http://louisa.levels.unisa.edu.au/~cisajs/1996/se/cap_jon2.html says:
>
>Capers Jones: Implementation of the Same Program in Three Languages
>
>Reference: Jones, Capers: Sources of error in software cost estimating,
>Version 1.0, November 24, 1993, Software Productivity Research,
>Burlington, MA 01803
>
>
> Macro
> Assembly Ada 83 C ++
> Source Code
> Required in LOC 10,000 2,000 1,200
>
> Activities Person-Months of Effort
>
> Requirements 2.0 2.0 2.0
>
> Design 4.0 2.0 0.5
>
> Coding 10.0 1.5 0.5
>
> Testing 4.0 1.5 1.0
>
> Documentation 2.0 2.0 2.0
>
> Management 2.0 1.0 0.5
>
> Total Project 24.0 10.0 6.5
>
> LOC/Staff Month
> (Total Project) 417.0 200.0 192.0
>
> Percent of Project
> for Coding and Test 50% 33% 23%
i would expect these figures to be out of date now, given Ada95, and
more mature C++ compilers that implement a greater part of the (soon to
be ratified) standard.